The latest time an activity may be completed without delaying the project finish date. The latest dates by which an activity can finish to avoid causing delays in the project. Many PM software packages calculate late dates with a backward pass from the end of the project to the beginning.

(Wideman Comparative Glossary of Common Project Management Terms v2.1)

J. Jerrald Hayes on FacebookJ. Jerrald Hayes on Twitter
J. Jerrald Hayes
I am ex-architectural woodworker and general contractor turned IT, Business and Project Management consultant, software developer wannabe senior division triathlete and ski racer, Yankee fan and founder of Paradigm-360.com, 360 Difference Mac4Construction.com,iOS4Construction.com and now TheBuildingAndRemodelingWiki.com too.
Share This